AI data centers can be built in under a year, but the energy systems needed to power them often take much longer to expand. On Wednesday, a data center disconnected from PJM, the major power grid serving all or parts of 13 states and the District of Columbia, causing power flickers in homes from Washington, DC, to Chicago. The incident highlights growing tension between rapid data center deployment and the slow, costly work of expanding electricity infrastructure.
The scale of demand is already large. Data centers used 176 terawatt-hours of electricity in the United States in 2023, about 4.4% of the national total, information from a Lawrence Berkeley National Laboratory study summarized by the Department of Energy. The study projected annual consumption could reach 325 to 580 TWh by 2028, or roughly 6.7% to 12% of US electricity generation. Its 2024 data center energy report reflects demand from conventional cloud computing and the growth of power-intensive AI workloads.
PJM’s forecasts show how concentrated that growth can be. The grid operator projected summer peak demand in its territory would rise from about 156 gigawatts in 2026 to 183 GW by 2030, an increase of roughly 17%. Data centers accounted for nearly 5,100 megawatts of a 5,250-MW increase in PJM’s 2027 to 28 peak-load forecast, according to a summary of its planning figures. Higher projected demand is also pressing on the region’s capacity market: a recent auction cleared at the price cap for a third consecutive time and fell 6.8 GW short of its reliability target. PJM’s independent market monitor, Monitoring Analytics, told federal regulators that 4,017 MW, or 42% of forecast data-center load growth, had been canceled or delayed.
That uncertainty complicates decisions about which facilities and grid upgrades to build. Utilities are seeking stronger customer commitments, credit requirements and transmission-security agreements before treating proposed data centers as firm demand. In one reported example, screening reduced a utility’s high-probability data-center load estimate from 18 GW at the end of 2025 to about 11 GW in the second quarter of 2026. These safeguards can limit the risk that existing customers pay for infrastructure serving projects that never proceed, but added requirements may slow viable projects.
Developers have also proposed bypassing the grid by generating power on-site. But supplying a large campus involves more than installing generation: new plants, substations and transmission lines must undergo interconnection studies. They also require permitting and equipment procurement, followed by financing and construction. Lawrence Berkeley National Laboratory research found that power projects reaching commercial operation in 2025 took more than five years from interconnection request to operation in regions with complete timing data. That measures power-project timelines, not the schedule for every data center, but it shows why new electricity supply may not be ready when a computing campus is.
The queue for proposed supply is large, but it does not represent electricity certain to be built. More than 2,061 GW of generation and storage capacity was in US interconnection queues at the end of 2025. Those projects still need to clear studies and, in many cases, secure upgrades and permits before financing and construction. At the federal level, the Federal Energy Regulatory Commission has directed six regional grid operators to explain or revise procedures for connecting large electricity users. The move focuses attention on reliability and cost allocation, including how to handle customers that delay or cancel requests.
The gap between data center construction and power infrastructure development creates risks for operators and utilities, as well as local communities. If forecasts overstate demand, customers could be left paying for underused upgrades; if grid investment falls short of actual growth, reliability and costs could come under pressure. As the AI sector expands, matching computing capacity with deliverable electricity is likely to become harder. This echoes concerns raised in other sectors, including shifts in advertising strategies discussed in recent coverage of open internet ad spend trends.